Home » Resources » Case Studies » Case Study – Ivinghoe Beacon, Buckinghamshire

Case Study Overview
Client

The National Trust

Location

Ivinghoe Beacon, Buckinghamshire

Industry

Land Management

Project Duration

October 2021

0.5 Hectares

Area subject to Search & Clear

UXO Finds

1 x Live High Explosive 2in Mortar

Challenge

In October 2021, 1st Line Defence was contacted by The National Trust regarding a site within a public park and conservation area, at Ivinghoe Beacon in Buckinghamshire.

Planned works comprised of the removal of vegetation to re-establish pathways and public access in the area – and a number of burning areas were identified to dispose of waste vegetation. At the time of the initial enquiry, the client was aware that the area had been formerly used by the military during WWII, and several items of UXO had recently been recovered from the site.

Based on this information and in consultation with the client, a bespoke UXO Risk Assessment was recommended plus an in-person site visit to discuss the project in more detail.

Process

Stage 1 – Detailed UXO Risk Assessment

1st Line Defence undertook a Detailed UXO Risk Assessment, which revealed that the area had been used by the British Army for training and billeting during the build up to Operation Overlord; the Allied Invasion of Normandy – during the first half of 1944.

It was also discovered that the British Army had conducted a number of Explosive Ordnance Clearance (EOC) tasks in the area of the site, dating back as far as the 1950’s. Archived newspaper reports also confirmed that in the 1960’s, a pupil from a local school found a ‘live’ 2-inch Mortar round in the vicinity of the site which resulted in injury.

Because of previous site use and history, the site was assessed to be at a ‘Medium-Risk’ of UXO contamination being present, and additional UXO risk mitigation was recommended.

Image showing aerial photography from 1945 of the site in Buckinghamshire with overlays highlighting ground disturbance close-by.
Stage 2 – Risk Mitigation Strategy

During the site visit and an examination of the site topography, 1st Line Defence was able to ascertain the likely firing positions within the site – and advise the client on the most probable areas in which EOC tasks had been completed.

We was also able to recommend to the client the most pragmatic way of mitigating the UXO risk within the main works areas, and 1st Line Defence recommended a UXO Search & Clear operation of three vegetation burning areas – and UXO Safety & Awareness Training for any new or existing staff conducting site clearance.

This methodology would cover all areas of the site that were being developed or accessed and if any UXO-related items were discovered, they could be checked, identified and removed safely – and the risk from UXO would be reduced to as low as reasonably practicable (ALARP) before ground works commenced.

Stage 3 – UXO Support

The Search & Clear team completed the investigation of the three burning areas, and a number of targets were identified for further investigation.

These items were investigated and a ‘live’ 2-inch Mortar round (pictured below) was recovered, plus some other items which were UXO-related scrap. The ‘live’ Mortar round was destroyed in-situ by local EOD authorities and the remaining items of UXO scrap were safely disposed of by 1st Line Defence.

Image of a ‘live’ 2-inch mortar round found during a Search & Clear operation at Ivinghoe Beacon in Buckinghamshire.

Outcome

Following the UXO Search & Clear operations, the risk from UXO was reduced to ALARP status – the client was able to safely dispose of the vegetation and complete the project on-schedule.

Latest Case Studies

Do you have a project in Buckinghamshire? Need advice but not sure where to start?

If you need advice about UXO risk mitigation in Buckinghamshire, contact us today and we’ll guide you through the process.

Call: +44 (0) 1992 245020 or Email: info@1stlinedefence.co.uk

Contact Us

* indicates required fields

This field is for validation purposes and should be left unchanged.